容积泵检查和控制beplay体育官网电脑Test Plan

This content provides you with example controlled volume pump inspection and test plan. You need to modify this ITP based on your project requirements.

受控音量泵检查和测试计划任务beplay体育官网电脑 小贩 TPI Inspection Client
Controlled Volume Pump Pre-inspection meeting, when specified by Purchaser H H R
Controlled Volume Pump Mill Test Reports H R R
Controlled Volume Pump Material identification and marking H W R
受控音量泵执行主要修理,当发出NCR时 H H R
Controlled Volume Pump RT, UT, MT or PT, when specified H R R
Controlled Volume Pump Heat treatment execution, if applicable H R R
Controlled Volume Pump Balancing test H W R
需要时控量泵夏比冲击试验 H W R
Controlled Volume Pump Hydrostatic test of casing H H R
Controlled Volume Pump Clearance check(Before/After the running test) H W R
Controlled Volume Pump Performance test H H R
Controlled Volume Pump Running test with vibration and bearing temperature measurement H W R
Controlled Volume Pump NPSH test, when NPSHA-NPSHR is less than 0.6m H H R
在运行测试期间控制音量泵声级测量 H H R
Controlled Volume Pump Dismantling inspection for casing internal, sleeve type bearing after test run, when specified H W R
Controlled Volume Pump Shop running test for lube oil unit, when provided and when libe oil unit is not used during pump running test. H W R
Controlled Volume Pump Shop running test for lube oil unit, when provided and when lube oil unit is used during pump running test. H W R
Controlled Volume Pump Hydrostatic test for lube oil unit, when provided H W R
Controlled Volume Pump Visual and dimensional inspection for lube oil unit, when provided H W R
控制的音量泵安装接线和导管(如果需要,如果需要,请执行以下操作) H W R
Controlled Volume Pump Function, setting and calibration of instruments and controls, when provided H W R
受控体积泵其他测试如指定 H W R
Controlled Volume Pump Final visual inspection (including Nameplate tagging marking painting coating Auxiliary items check) H H R
Controlled Volume Pump Documentation review prior to release (Final activity of Technical Inspection) H H R
Controlled Volume Pump Pre-shipment Inspection H H R

H:保持点implies that relevant production activities shall not proceed until the continuation of work is permitted by Purchaser. (Notification req'd)

W: Witness pointimplies that Purchaser intends to witness the designated inspection feature. If Purchaser decides not to witness the relevant feature, production can proceed without permission of Purchaser. (Notification req'd)

S: Witness,but spot check basis. Initial operation will be witness point and subsequent operation will be witnessed at discretion of Purchaser considering the results of previous inspection. (Random Inspection : Notification not required)

R: Reviewinspection & test records (Notification not req'd)

General Note :

1) Controlled Volume Witness / hold point by Code Inspector, when applied by Code Stamp / Local Regulation, is to comply with its requirements and to specify in Vendor's ITP.

2) Type of Inspection by Controlled Volume Purchaser may be changed according to equipment criticality and vendor QC evaluation at job stage.

3) When requested in the requisition, detailed Controlled Volume ITP shall be submitted by Vendor.

4) Monitoring / Observation of Controlled Volume Vendor shop daily routine works (i.e. Storage of materials & welding consumables, Adherence to approved procedures, Testing tool calibration check,Welder/NDE Operator performance & qualification, workmanship, cleanliness and etc.) shall be done by Purchaser during inspection visit.

5) Final Controlled Volume Visual Inspection/Documentation Review / Pre-Shipment Inspection may be combined within one time visit.

6) Based on Controlled Volume Supplier's quality control system and quantity of purchase order can be held or waived at the discretion of purchaser.


Return from Controlled Volume Pump Inspection and Test Plan to Inspection and Test Plan

Return from Controlled Volume Pump Inspection and Test Plan to Inspection for Industry Home


Did you find this article useful? Click on below Like and G+1 buttons!

New!注释

让你说到你刚刚阅读的内容!在下面的框中给我发表评论。
Baidu